First Cost Basics
Building and HVAC System Criteria drive Costs
- Building Type, Occupancy and Use
- Thermal Zones and Ventilation Requirements
- HVAC Equipment Space Allocation
- Central System vs Distributed / Unitary System
Generally, the Geothermal system cost inside the building is less than or equal to conventional system
Incremental cost of a Geothermal Heat Exchanger vs
- Boiler and Heating Water Pumping systems
- Chiller / Cooling Tower and related Pumping systems
- Condensing Units / Rooftop Units
First Cost is greatly influenced by Effective Design
First Cost Considerations
Manage the Installed Cost
- Reduce the total Heating / Cooling Load
− Efficient Building Envelope
− Outside Air Loads: CO2 / DCV and Energy Recovery Units
− Recognize System Load Diversity - Field Test for actual Soil Thermal Conductivity
- Organize and Minimize Geothermal System Piping
- Control the Control System Costs
- Experience based evaluation of System Design
Recognize All System Related Cost Savings
- Boiler Stacks and Roof Penetrations
- Boiler Room Combustion Air
- Chemical Treatment, Make Up Water and related equipment
- Structural Cost for Cooling Tower or Equipment Support
- Screen Walls and Fences for Vision, Vandalism, Security
- Machine Room (Refrigerant) Ventilation
- Natural Gas Service Entrance
- Reduced Mechanical Equipment Floor area
Utility Company Incentives
- $ 0 to $ 600 per ton
- Custom Incentive Programs
- Alternate Rate Schedules
- Check with the Local Utility before Design
Financing Options
- Energy Savings or Performance Contracting
- Utility Company Financing
Tax Incentives
- Up to $1.80 per SF for 50% better than Energy Standard
- Up to $300 Tax Credit for Residential Geothermal Heat Pumps
First Costs – Geothermal Bore Field
Unit Cost Summary – 14 Building
These are project reported construction costs
- The costs are not qualified for scope or normalized for conditions
- Costs do not include Credits for Boilers, Chillers, Cooling Towers
- Costs do not include Utility Company Incentives
- Additional Project Cost Information appreciated
First Cost Examples
West Liberty High School
- New High School 78,000 GSF with 280 tons cooling capacity
- Horizontal Bore Installation Alternate bid
- 112 Horizontal Bores at 500 feet long
- Horizontal Bores stacked two high
- $363,000 for Horizontal Bore Field piped to Building
- $3232 per bore / $6.46 per bore foot
- Vertical Bore arrangement bid at $160,000 more (44% increase)
Energy Costs
All Electric / Electric Heat Rate Schedule
- Significant Factor for Energy Costs
- Identify the applicable Rate Schedule
- Electric Costs of 4 ¢/KWH electric heat vs. 8 ¢/KWH for winter use
- Some Rates may be applied to the total building electrical use
- Net Heating Energy Costs of $4/MMBTU vs. $12/MMBTU
Electrical Demand
- Typical Reduction in Electrical Demand
- Demand Limiting / Load Shedding Opportunities
- Demand may be a significant factor in total electric costs
Case Studies – Three Ankeny Elementary Schools
- Actual Site Energy Reduction: 46% to 54% BTU/SF-Yr
- Actual Energy Cost Reduction: 6% to 14% $/SF-Yr
Non Air Conditioned to Air Conditioned - Energy Cost Avoidance: 20% to 34% $/SF-Yr
Economic Performance
The Bottom Line
Most Energy Efficient Heating & Cooling System Available- Comfortable with a High Degree of Owner Satisfaction
- Reduces Energy Cost by 20% to 35%
- Adds 2 – 4% to the Total Cost of New Construction
- Incentives, Credits and Alternate Financing may be Available
- Typical 5 to 10 year payback
- Generally best Life Cycle Costs
Each Commercial Facility is Unique

